FAQs

FAQs2025-09-03T10:11:43-07:00

Please note that the FAQs under the FEMA tab are provided directly by FEMA and not the City of Malibu.

Can you please provide a range of illustrations, as examples, of FEMA-acceptable designs for breakaway walls and garage doors besides lattice and screenings?2025-09-03T09:48:13-07:00
Are there Permit Exemptions for Exploratory Borings?2025-08-26T10:54:26-07:00

For the Broad, Franklin, and Palisades Fire rebuilds, geologic/geotechnical exploratory borings are exempt from requiring excavation permits. 

This exemption was confirmed by the Building Official to help streamline the early stages of rebuilding.  

What is temporary housing? Is this an option for me?2025-08-26T10:55:37-07:00

Temporary housing structures are defined as mobile homes, trailers, recreational vehicles or other structures which are self-contained units which include sanitary facilities, and facilities for normal daily routines including cooking and sleeping. Temporary housing structures DO NOT include any structure placed upon a permanent foundation, nor do they include tents, yurts, or similar fabric or textile installations. 

To find out if temporary housing is an option for you, contact: Yolanda Bundy, Community Development Director (ybundy@malibucity.org) and Ryan Cerny, Supervising Building Inspector (rcerny@malibucity.org). 

For more details, review the Temporary Housing Permit Booklet.

Can service utilities, machinery and equipment be physically attached to a breakaway wall inside the garage/ enclosure area?2025-09-03T08:55:22-07:00

No. Utilities, including electrical wiring, switches, outlets, breaker boxes, power meters, plumbing, conduits, and ventilation ducts, are not to be placed in or attached to breakaway wall panels. Building supply lines and other utility fixtures, such as light switches or electrical outlets, may be attached to the sheltered side of vertical foundation members as allowed by applicable building codes and floodplain management regulations (which generally require that utilities be elevated above the BFE). Breakaway walls are discussed in TB-9 and in ASCE 24 and FEMA Mitigation Assessment Team (MAT) observations described below:

  • ASCE 24-14, Section 4.6.1 Breakaway Walls. Requires breakaway walls to fail before or during base flood conditions without imparting loads on foundations and without producing damaging debris. Specifies that utilities and equipment must not be mounted on, pass through, or be located along breakaway walls.
  • MAT observations: All utility components that must be installed below the elevated structure must be flood damage-resistant, designed for flood forces, and attached to permanent structural elements. When utilities must be located below an elevated structure, the components should be placed on the protected side of a foundation member on the side opposite to the anticipated direction of flow and wave approach.
If the DFE is, for example, 8-feet within the garage/ enclosure area, can there be solid walls above the DFE? And can service utilities, machinery and equipment be installed above the DFE on the solid walls?2025-09-03T08:55:51-07:00

No. In Coastal areas, DFE is the bottom of lowest horizontal structural member, therefore there should be no “solid walls” between that and the top of the breakaway wall.

Can you please confirm that a garage floor/slab that is below the DFE must have breakaway walls on all sides of the enclosure area? Also, does this mean that the living/habitable area above the garage must be supported on piles, piers, or columns?2025-09-03T08:58:17-07:00

Confirmed. Breakaway walls are not a requirement on open foundations. A garage floor/slab below the BFE can remain open, be enclosed by insect screening or lattice work, or enclosed by breakaway walls. Also, since breakaway walls are not structural, the living area above the garage will have to be supported by structural piles/piers/columns.

If the DFE is, for example, 8-feet, does this mean that the elevation of the bottom portion of the lowest horizontal support member/ structure that supports the above living/ habitable area must be at least 8-feet? The 8-feet is not the top of the finished floor of the living / habitable area, correct?2025-09-03T08:58:44-07:00

Yes. The elevation must be referenced to the bottom of the lowest horizontal structural member if the structure is located in a V Zone or Coastal A Zone. If the structure is located outside of the V and Coastal A Zones, then the elevation can be referenced to the top of the floor.

Please explain the terms prescriptive breakaway wall’ and ‘frangible’.2025-09-03T09:46:56-07:00

Prescriptive breakaway walls are code compliant, with resistance between 10 and 20 psf. If the breakaway resistance exceeds 20 psf, then an engineer must certify that the wall will fail under base load loads with no damage to the structure.

Frangible building elements are ones that are designed to break into small pieces that will not cause an obstruction to flow or damage other structures. Examples of frangible elements include breakaway walls as well as small non-structural slabs with saw-cut joints beneath elevated coastal buildings.

Is FEMA concerned about floating/ migrating breakaway pieces of the house/garage during a flood event that move off the property and physically hit/ impact adjacent structures on neighboring properties? Does this potential occurrence need to be addressed in order to be compliant with the NFIP?2025-09-03T09:47:26-07:00

Yes, this is a FEMA concern regarding breakaway walls. Additionally, ASCE 24-14, Section 4.6.1 (Breakaway Walls) requires breakaway walls to fail before or during base flood conditions without impacting loads on foundations and without producing damaging debris.

Does the City have an official list of building professionals?2025-08-26T10:53:18-07:00

The City does not maintain its own contractor list, but the Malibu Pacific Palisades Chamber of Commerce does!

If you’re an architect, engineer, contractor, or designer and want to be listed, contact: (310) 456-9025 | CEO@Malibu.org  

Please provide a typical list of service utilities, machinery and equipment that must be elevated to the DFE. Also, if these cannot be elevated to the DFE, please explain ‘floodproofing’ and how this can be achieved that is FEMA-acceptable.2025-09-03T09:51:43-07:00

A list of utility services, machinery and equipment that must be elevated to the DFE can be found in FEMA P-348, Protecting Building Utility Systems from Flood Damage, Edition 2, February 2017. If these services, machinery and equipment cannot be elevated, then the NFIP states they must be designed and constructed to prevent entry and accumulation of floodwaters. While this is very difficult to achieve, examples of FEMA-acceptable ‘floodproofing’ techniques may include placement of below-BFE utilities in a flood-resistant enclosure such as a low floodwall or a large floodproof vault.

Can flood vent openings be installed in breakaway walls in the hope that flood water forces might reduce the risk of wall collapse? Does the one-square inch of net opening for every one-square foot of net opening apply?2025-09-03T09:52:23-07:00

TB-9 (3.3): The 2015 and later editions of the IRC and the 2014 edition of ASCE 24 require flood openings in breakaway walls in both Zone A (including Coastal A Zones) and Zone V. Breakaway walls with flood openings must be designed to fail under the base flood specified by the NFIP regulations and building codes and standards. The NFIP regulations do not require flood openings in breakaway walls of enclosures below elevated buildings in Zone V but require flood openings in walls of enclosures below elevated buildings in Zone A, even when breakaway walls are specified. See NFIP Technical Bulletin 1, Requirements for Flood Openings in Foundation Walls and Walls
of Enclosures.

Besides the Comments Section on the Elevation Certificate, are there any other boxes on the EC that need to address breakaway wall installation?2025-09-03T09:52:51-07:00

No. We are not aware of any additional EC boxes that need to address breakaway wall concerns.

If the elevation of the garage slab is below the DFE, can the design share the same foundation members (piles) for the house if the living area of the house is directly above the garage?2025-09-03T09:53:20-07:00

Yes. According to ASCE 24-14 (9.3): In Coastal High Hazard Areas, Coastal A Zones, and other High Risk Flood Hazard Areas, concrete slabs used as parking pads, enclosure floors, landings, decks, walkways, patios, and similar uses shall be permitted beneath or adjacent to structures, provided the concrete slabs are designed and constructed as described below:

  1. To be structurally independent of the primary foundation system of the structure, to not transfer flood loads to the main structure, and to be frangible and break away to minimize the debris capable of causing significant damage to any structure. Reinforcing of concrete slabs, including welded wire reinforcement, shall not be used to minimize the potential for concrete slabs being a source of debris. Slabs shall not have turned down edges, and maximum slab thickness shall not exceed 4 in.; or
  2. To be self-supporting structural slabs capable of remaining intact and functional under base flood conditions, including expected erosion or uplift pressures, and the main structure shall be capable of resisting any added flood loads and effects of local scour due to the presence of the slabs.
TB4 Elevator Installation (for V-zone).2025-09-03T09:53:46-07:00

The Coastal Construction Manual course addresses this topic.

Per TB-4 (3.2), elevator shafts must resist flood loads. In Zone A, shafts are not required to have flood openings; in Zone V and Coastal A Zones, shafts are not required to have breakaway walls. In addition, (6.1) to minimize flood damage, elevator shafts/enclosures must be designed to resist hydrostatic, hydrodynamic, and debris impact forces, as well as erosion, scour, and waves, particularly in Zone V. To reduce exposure of elevators to flood loads, a common practice is to construct reinforced masonry block or reinforced concrete elevator shafts and locate them on the landward side of buildings in coastal areas and on the downstream side of buildings in riverine floodplains. Furthermore, designs for nearby or adjacent structural elements of the building should take into account the impacts of obstructed flow.

What MEP (mechanical, electrical, plumbing) can be below BFE.2025-09-03T09:54:20-07:00

Per FEMA P-348 (3.2.3): although difficult to achieve, an alternative provided by NFIP regulations allows equipment to be located below the BFE, provided that the equipment is designed, constructed, and installed to “prevent water from entering or accumulating within the components during conditions of flooding.” Please note that specially designed equipment is not permitted below the BFE in buildings located in coastal high-hazard areas (Zone V) due to a requirement that space below such buildings be free of obstructions.

Detached garages (split level design to accommodate a garage below BFE): How much space needed between the home and garage to be considered detached, access/entrance between the two. [see diagram below, where street Pacific Coast Highway (PCH) is below BFE]2025-09-03T09:54:57-07:00

We are consulting with a subject matter expert on this one. Please allow more time to answer this question.

 

 

 

Need to Locate Permits for Your Property?2025-08-26T10:48:17-07:00

If your structure was damaged or destroyed, you can search for existing permits and records through the Malibu Rebuilds Permit Portal. 

Access it here: https://maliburebuilds.org/records/  

Will excavation permits for borings be exempt?2025-08-04T14:49:04-07:00

Excavation permits: Borings (Geologic/Geotechnical/Exploratory Excavation Borings) will be exempt from permits for Broad, Franklin and Palisades fire rebuilds per the Building Official Determination.

How can I learn more about Phase 1 & 2 of fire debris removal?2025-07-09T16:47:35-07:00

For more information about debris removal, visit our Removal Process, Foundations and Onsite Wastewater Treatment Systems pages.

How are mudslide risks being addressed during rainy weather?2025-02-07T15:39:41-08:00

The Los Angeles County Department of Public Works, in collaboration with the City of Malibu, is preparing for mudslide risks in accordance with the National Weather Service’s Debris Flow Survival Guide. 

What precautions should I take regarding ash and toxic materials?2025-02-07T15:39:58-08:00

Residents should follow guidance from the LA County Department of Public Health when handling ash and toxic materials after returning home. Please ensure you are taking proper safety precautions to ensure a safe return home. 

Where can I find consolidated information about available resources and assistance?2025-07-09T20:55:17-07:00

You can visit our Small Business Resources and Community Resources pages for information on key resources.

What emergency alert systems are available?2025-03-17T15:28:16-07:00
Who do I contact for specific concerns?2025-07-09T16:34:46-07:00

Visit our Contact Us page for more information including the Contact Us form, Malibu Rebuild Center information and more.

How do I stay informed about updates?2025-08-04T14:54:28-07:00

We encourage all residents to sign up for our bi-weekly Malibu Recovery & Rebuild Newsletter and all businesses to sign up for the Malibu Business Resources & Updates newsletter.

Residents can continue to get updates about the Palisades Fire and the ongoing rebuild process here:

We also recommend following the City’s social media accounts, which will post the latest updates as they are available.

How can I initiate the rebuilding process?2025-08-04T15:03:48-07:00

To begin the rebuilding process, you will start by confirming your property is within City limits using the City’s GIS and obtaining your property records. For more information on the rebuilding process, visit the Rebuilding Steps page.

Check out the Rebuild Roadmap below for more info on the development portal and the rebuild process.

Will the review process be concurrent between Planning and Building & Safety?2025-01-22T16:48:54-08:00

In some cases, concurrent submittals may be warranted to speed up the process. For the most part, rebuilds in-kind will see quick planning approval and so there may not be a need for concurrent submittal. After receiving planning approval, the application will go through the plan check process with Building Safety before a permit is issued.

How do I add my business to the list of contractors provided to the public?2025-02-07T11:55:34-08:00

The City of Malibu appreciates your desire to help our residents during these difficult times. The City of Malibu does not
maintain its own list of contractors. However the Malibu Pacific Palisades Chamber of Commerce maintains a list of professional contacts for architects, engineers, general contractors, designers, and subcontractors. Please reach out to them for more information on how to be added to this list at (310) 456-9025 or CEO@Malibu.org.

Will there be any fee waivers for rebuilding?2025-08-26T10:49:40-07:00

The City of Malibu has launched a Fee Waiver Program to help property owners rebuild by eliminating City planning and building permit fees for like-for-like, owner-occupied homes. To save residents time and hassle, City staff will prepare the required affidavit on behalf of each qualifying property owner. To learn more, visit: maliburebuilds.org/feewaiver

Am I able to stay on my property while I process an application to rebuild?2025-07-24T09:39:19-07:00

A temporary, owner-occupied trailer or mobile home may be placed onsite if permits are obtained with certain conditions of approval. Debris clearance must be completed and a City-registered OWTS practitioner must verify that there is a functioning onsite wastewater treatment system (OWTS, also known as a septic system) before permits may be issued. A Temporary Housing Permit Booklet, as well as other information, can be found at MalibuRebuilds.org.

Do I need a permit to install erosion control devices for storm preparation?2025-08-04T15:07:56-07:00

Erosion control devices help control or prevent wind- or water-induced erosion of exposed soil and debris. Normally, review and approval from the Building Safety Division is required before these devices can be installed. This will help ensure they are installed properly and do not cause further damage to the property or a neighboring property. However, if rain is expected in the upcoming 24 to 48 hours, property owners may proceed to put erosion control measures in place without obtaining a permit. For additional information, visit the Storm Preparation page.

Can I use any remaining structural elements?2025-04-03T18:27:17-07:00
  • OWTS – Onsite wastewater treatment systems (OWTS), sometimes called septic systems, need to be inspected by a City-registered OWTS practitioner to verify their functionality before they can be used for either a permanent rebuild or a temporary trailer. Most of the components of an OWTS are located below ground and are typically more resistant to fire damage. Damage to an OWTS may have occurred due to high heat, exposure to flames, smoke, ash, and power outages or equipment failure. Heavy firefighting equipment and heat from fires may also damage underground OWTS components, such as fiberglass tanks, piping, and old system components. In addition, fire materials may have contaminated the contents of tanks, and the liquid and waste may need to be pumped out. A City-registered Practitioner must inspect the OWTS for signs of damage and functionality of components and submit an OWTS inspection form prior to utilization of the system.
  • FOUNDATIONS – The re-use of other structural elements, such as existing foundations in fire-damaged buildings and structures require a feasibility review by the City’s Environmental Sustainability Department. This review only considers the durability and soundness of concrete foundations, including slabs, footings, piles, and retaining walls, based on the testing data described below. Find out more information about foundation feasibility reports by viewing the Foundation Feasibility Report for Fire-Damaged Structures and Foundation Re-Use after a Wildfire.
  • CHIMNEYS AND FIREPLACES – The re-use of chimneys and fireplaces still standing after the completion of the debris removal process requires the confirmation of structural stability by a structural engineer. Fireplaces and chimneys destroyed or removed may be replaced per the permit process described below however, note that all new fireplaces must be gas-burning, as state law prohibits the construction of new wood-burning fireplaces.
Go to Top